Can Variations Be Charged Without Written Approval?

Builder and homeowner discussing kitchen renovation plans and countertop options

Can Variations Be Charged Without Written Approval?

In Queensland, variations generally cannot be charged without written approval. Most residential building contracts require variations to be agreed in writing before the builder carries out the work or charges for it. Written approval is also part of the Queensland Building and Construction Commission Act 1991 requirements. If a variation is not properly documented, the builder may struggle to enforce payment, and the homeowner may dispute the cost.

If you’re building or renovating in Queensland, you’ve probably already heard the word “variation” more times than you expected. Variations are changes to the original scope of work – anything from upgrading tiles to moving a wall. They’re common, but they’re also one of the biggest sources of disputes between homeowners and builders.

The key question many people ask is whether a builder can charge for a variation without written approval. The short answer is no. Under Queensland law, particularly for domestic building work, variations must be properly documented and agreed in writing before the builder can charge for them. This protects both parties and ensures everyone understands the cost and impact of the change.

What is a contract variation?

Before diving into the legal rules, it helps to understand what a variation actually is. In construction, a variation is simply any change to the original scope of work set out in your signed building contract.

Variations can happen for a wide range of reasons, including:

  • Client-requested changes, such as upgrading kitchen benchtops or adding extra power points.
  • Site conditions, such as encountering unexpected rock during excavation that requires specialised machinery.
  • Design modifications, such as structural adjustments required by an engineer or building certifier.
  • Substitution of materials, when a specified product is out of stock or discontinued.

Variations can either increase the contract price (an addition) or decrease the contract price (a negative variation) depending on the subject issue of the variation. Regardless of who suggests the change, it alters the binding agreement you made with your builder.

The strict Queensland rule: Get it in writing before work starts

In Queensland, residential building contracts are governed by strict consumer protection laws. Schedule 1B of the QBCC Act sets out a very clear process that builders must follow before performing any variation work.

Under the law, before any variation work begins, your builder must:

  1. Prepare a written variation document (often using a standard QBCC Form 4 or Form 5).
  2. Clearly describe the proposed changes to the scope of work.
  3. State the date of the request and provide a reasonable estimate of any delay the change will cause.
  4. State the exact change in contract price or explain the precise method used to calculate the cost.
  5. Provide this written document to you for review and obtain your signed, written agreement.

Once both parties agree in writing, the builder must also provide you with a copy of the signed variation within five business days, or before the variation work actually starts – whichever happens first.

If a builder fails to follow this statutory process and goes ahead with extra work without your written sign-off, they are breaching Queensland law. In fact, failing to put variations in writing is an offence that can lead to fines and demerit points against the builder’s QBCC licence.

Even if the variation is one you have requested as an owner, the ABCC Act makes the Builder responsible for documenting the variation.

Are there any exceptions to the rule?

Because the law is designed to protect consumers of building services from budget blow-outs, the exceptions to the written approval rule are narrow.

The main statutory exception is an emergency. If urgent variation work is required immediately, for example, to prevent safety hazards or severe property damage, and it is not reasonably practical for the builder to produce a written document first, they may proceed. However, even in emergencies, the builder must document the variation in writing as soon as practical afterwards.

The only other avenue for a builder to recover money for an unapproved variation is by applying to the Queensland Civil and Administrative Tribunal (QCAT) for approval. To succeed, the builder faces a very high legal bar. They must prove to the tribunal that:

  • Exceptional circumstances exist, or they would suffer unreasonable financial hardship if not paid; and
  • It would not be unfair to the homeowner to order payment for the work.

Because the statutory rules requiring written approval are well known across the industry and the requirements are consumer protection provisions, QCAT takes a very strict approach. Tribunals rarely reward builders who don’t do their paperwork.

What if the homeowner requested the change verbally?

Even if the homeowner asked for the change, the builder still needs to submit the written variation complying with the QBCC Act and obtain written approval. A verbal request does not replace the legal requirement for a written variation, although a verbal request by the owner, with other circumstances, may be relevant to an application for approval to QCAT.

Homeowners sometimes assume a small change won’t cost much, only to be surprised by a large invoice later. Written approval ensures transparency and protects both sides.

If you’re unsure whether a change will cost extra, ask your builder to provide a written variation before any work begins.

What should homeowners do before approving a variation?

Before agreeing to any variation, homeowners should:

  • Read the proposed variation carefully.
  • Understand exactly what work is changing.
  • Confirm the additional cost.
  • Ask whether extra time will be required.
  • Keep copies of all documents.
  • Avoid giving verbal instructions on site.

If something is unclear, ask questions before signing the variation rather than after the work has been completed.

What should builders do?

Builders can significantly reduce disputes by following good documentation practices.

This includes:

  • Providing written variation documents before commencing additional work.
  • Explaining the reasons for the variation.
  • Clearly identifying any additional costs.
  • Obtaining signed approval wherever possible.
  • Keeping records of emails, messages and site discussions.
  • Updating project schedules where completion dates change.

Clear communication often prevents disagreements from developing into formal disputes.

What happens if there is a dispute?

If a disagreement arises about a variation, the first step is usually to review the building contract and any written communications between the parties.

Many disputes can be resolved through negotiation once everyone understands what was agreed.

Where agreement cannot be reached, alternative dispute resolution processes such as mediation may assist. Depending on the nature of the dispute, matters may ultimately be determined by the Queensland Civil and Administrative Tribunal (QCAT) or a court.

Obtaining legal advice early can often help identify the strengths and weaknesses of each party’s position before legal costs escalate.

Final thoughts

Variations are a normal part of many construction projects, but they should never be treated as an informal conversation or handshake agreement. While there are limited situations where a builder may be able to charge for additional work without written approval, Queensland law and most building contracts strongly favour written variations that clearly record the scope of the changes, the cost and any impact on the construction timeline.

Whether you are a homeowner or a builder, taking the time to document variations properly can help prevent expensive disputes and keep your project on track. If you are facing a disagreement about unpaid variation claims or believe a variation was not properly authorised, obtaining advice from an experienced Queensland construction lawyer can help you understand your rights and the most appropriate way to resolve the issue.

To contact Leslie:  leslie@clarkmoore.com.au or call on 0417 783 075

To contact Leslie:  leslie@clarkmoore.com.au or call on 0417 783 075

Disclaimer: The information provided in this blog is for general informational purposes only and does not constitute legal advice. While we strive to ensure the accuracy and reliability of the information, it is subject to change and may not reflect the latest legal developments. Readers should not act upon this information without seeking professional legal advice specific to their situation. Clark Moore Legal disclaims any liability for actions taken based on the content of this blog. For tailored legal advice, please contact us directly.